Construction Timeline

18-month Overview

Demolition of Existing Memorial Bridge   January-May 2012
Construction of New Foundations   May-August 2012
Construction of Substructure   June-September 2012
Construction of Scott Avenue Approach Superstructure   September-December 2012
Construction of Kittery Approach Superstructure   September-December 2012
Steel Fabrication of Spans   September 2012-April 2013
New South Span Float-in   January 2013
New North Span Float-in   March 2013
New Lift Span Float-in   June 2013
Bridge Opens   August 8, 2013!  Enjoy!
NOTE: All timing is approximate based on weather and other factors.

 